Update – January 5th, 2006

They framed and poured the concrete footers today.  This has to cure for a couple days and has to be inspected by the city before the basement wall moulds can go up and be poured.  That is slated for Monday the 9th at the earliest.  In the meantime they will probably put stone down on the ground around the footers.