Backfill, Driveway, and Steel…

On Monday the 16th the basement was shored and backfilled with stone. You can see the boards all still in place which reinforced the basement walls during the backfill process. They remain there for a day or so until the concrete has had time to harden a bit more. In the meantime, stone was poured for a temporary driveway as well as where the porches and garage floor will be poured later. The steel beams and support poles were delivered today and the first floor lumber is supposed to arrive tonight as well. Tomorrow they will start the framing process and it will be completed very quickly!